An A-Permit for Street Trees is required for the installation of a tree in the public right-of-way. An additional permit from the Bureau of Street Services, Urban Forestry Division may be required to either remove, prune, or trim the roots of a tree. This Bureau of Street Services (BSS), Urban Forestry Division is located at 1149 S. Broadway, 4th Floor, Los Angeles, Phone: 213-847-3077. If an applicant removes trees and decides not to replant, Applicants will be required to pay a special fee per LAMC 62.177 - Establishment of Tree Replacement and Planting In-Lieu Fee.
The following is the BOE vetting process that will take place once a completed application is received. Instructions on how to complete the on-line A-Permit application can be found in this manual under Construction "A" Permits, Technical Procedures, 01 - Permit Processing Procedures for Construction A-Permits.
PERMIT PROCESSING
- Determine if this permit is an A- or B-Permit. A-Permit projects are not generally part of a large development project. For example, a large development project where tree installation is part of a larger project and requirements. If trees are required as a condition of a Planning Case, the Urban Forestry Division of the Bureau of Street Services will let the B-Permit group know of their requirements regarding the number, size, and location of trees to be planted. Another example of a B-Permit project would be if the scope of work included a street widening or other major street improvements where the installation of street trees would be included as part of the project.
- B-Permit group will determine if a B-Permit is needed to complete the job. If not they will direct the applicant to the A-Permit counter.
- B-Permit group will prepare a Municipal Cash Bond (MCB) or instruct the applicant on how to process a Surety bond.
- B-Permit group will prepare a Condition Clearance Letter for the Land Development Group.
- If an A-Permit, the following are required in order to start the A-Permit application:
- Permittee will need to have an approved Surety Bond or Cash bond in hand, in order to pay for maintenance fees of each tree
- BOE may be asked to provide an estimate to the Applicant in order for the Applicant to obtain a surety bond. This is done through the "Fee Estimate" tab on the left menu (directions for this process are located in the Permit Processing Procedures for A Permits document)
- A fee for each tree well will also be added to the permit if the trees are to be planted in the sidewalk (public right-of-way)
- BOE staff to enter the Bond # in the remarks section of the application
- Applicant will be required to pay for the permit fee and the cash bond (if not a surety) prior to issuance of the A-Permit
- BOE staff shall send a copy of the A-Permit to BSS, Urban Forestry
- Permittee will need to have an approved Surety Bond or Cash bond in hand, in order to pay for maintenance fees of each tree
- If the permit is part of the "City Plants" program, then only the Basic Fee and surcharges are collected. In addition, the following is required:
- Use a central address near the middle of the project
- Indicate on the Permit this is for “City Plants”
- Inspection is by BSS Urban Forestry Division
- Indicate the number of tree wells to be installed but waive fees
- Change inspection contact to BSS Urban Forestry Division